Caltrans plans overnight Sepulveda Pass closures on I-405 and paving closures on US-101 in the Cahuenga Pass from Monday, Nov. 30, through Friday, Dec. 4. Crews work at night, and schedules can shift with weather.
Both jobs are long projects, so similar notices will keep coming. The I-405 work is part of a $143.7 million pavement project between Van Nuys and Westwood. As of Nov. 26, 2026, Caltrans has not posted an end date in the notices we reviewed.
Sepulveda Pass closures on I-405
According to a Caltrans release published by SCVNews, work runs from 9 p.m. to 6 a.m. for median barrier work and paving. The speed limit drops to 55 mph in some sections.
Northbound, up to four lanes close between Sepulveda Boulevard and Victory Boulevard. Up to two lanes close between Wilshire and Skirball Center Drive/Mulholland Drive. Ramps closed northbound are Getty Center Drive on and off, Burbank Boulevard on and off, the Victory Boulevard off-ramp and the Sepulveda Boulevard on-ramp.
Southbound, up to four lanes close between Skirball Center Drive/Mulholland Drive and Wilshire Boulevard. Up to three lanes close between Victory Boulevard and US-101. The Burbank Boulevard ramps close in both directions. Three US-101 connectors to I-405 also close: northbound 101 to both I-405 directions, and southbound 101 to northbound I-405.
Cahuenga Pass paving on US-101
Caltrans published its Cahuenga Pass notice on Nov. 24. Northbound 101 drops to two lanes between Highland Avenue and SR-170 overnight, then to one lane from 2 to 4 a.m. Southbound 101 drops to three lanes between SR-170 and Cahuenga Boulevard.
Several connectors close fully, usually from 11:59 p.m. to 5 or 6 a.m. They include the Hollywood Freeway to northbound Ventura Freeway connector and the southbound 101 to eastbound SR-134 connector. The southbound Ventura Freeway to Hollywood Freeway connector also closes, as does southbound SR-170 to southbound 101 from 10 p.m. to 5 a.m.
The detours use Vineland Avenue. For example, drivers heading to eastbound SR-134 exit at Vineland, go north, then turn east on Riverside Drive. Friday night, Dec. 4, closures run later, until 7 to 9 a.m. Saturday.
What drivers can do
Allow extra time between 9 p.m. and 6 a.m., and check the Caltrans I-405 project page before you leave. Surface streets such as Sepulveda Boulevard may carry more traffic when ramps close. For earlier weeks of work, see our Cahuenga Pass paving report. More transport news is in our Los Angeles hub.